Pricing Change
New pricing for orders of material from this site will come into place shortly. Charges for supply of digital images, digitisation on demand, prints and licensing will be altered.
Upcoming Maintenance
Please be advised that this website will undergo scheduled maintenance on the following dates:
Thursday, 9 January: 11:00 AM - 3:00 PM
Thursday, 23 January: 11:00 AM - 3:00 PM
Thursday, 30 January: 11:00 AM - 3:00 PM
During these times, some functionality such as image purchasing may be temporarily unavailable. We apologise for any inconvenience this may cause.
Loch Sloy hydroelectric scheme, 1945-50
Date 26 October 2023
Event ID 1165389
Category Descriptive Accounts
Type Note
Permalink http://canmore.org.uk/event/1165389
The Loch Sloy hydro electric scheme
This was the first scheme to be tackled in 1945. Serious problems arose due to the post-war shortages of manpower and materials. The first of these was addressed by using hundreds of German prisoners of war. Access problems required the building of roads and conveyors for materials landed from Loch Lomond. Severe weather conditions delayed progress and the project was not completed until 1950.
A dam of massive buttress type was built at the south-eastern end of Loch Sloy leading to a tunnel through Ben Vorlich, followed by four circular pipelines leading to to the Loch Sloy power station at Inveruglas on the side of Loch Lomond. A surge shaft was incorporated in Ben Vorlich.
The generating sets consist of four vertical shaft Francis turbines each coupled to a 32,500 kW alternator. Delays due to adverse weather continued and transport problems for the heavy equipment which was finally installed by 1950. When fully loaded the turbines pass a million gallons of water per minute.
Information from NRHE item catalogue number WP007424 compiled by George Walker in 2005.